CMS

As part of the measures to refuse the use of ADSL communication lines and the transition to a fiber-optic line, it was decided to lay fiber on the territory of the Promtractor PC in the workshops of the BMC, PSC, KOT.

The laying of the fiber-optic line was carried out by the OIC specialists.

As of 12.04.2023, more than 200 users have been transferred

At the first stage of the work, 80 users were connected, including 30 priority ones. At the second stage, it was planned to connect 170 users to the new high-speed fiber-optic communication line (at a speed of 100 MB/s) (now the data exchange rate does not exceed 2 MB/s).

The commissioning of a new fiber-optic communication line made it possible to increase the speed of information exchange and the access of PC Promtractor users to data by about 100 times (it was 2 mb/s became 100 mb/s)

BMC

Title

Total

Installed

Done
%

Switching cabinets

17

17

100,0%

Laid an optical cable to

17

17

100,0%

Twisted pair laid

14

14

100,0%

Welded fibers

38

38

100,0%

Installed sockets

14

14

100,0%

The power supply is connected to

17

16

94,1%

99,0%

PSC

Title

Total

Installed

Done
%

Switching cabinets

21

20

95,2%

Laid an optical cable to

21

21

100,0%

Twisted pair laid

17

17

100,0%

Welded fibers

16

16

100,0%

Installed sockets

17

17

100,0%

The power supply is connected to

17

17

100,0%

99,2%

КОТ

Title

Total

Installed

Done
%

Switching cabinets

6

6

100,00%

Laid an optical cable to

6

6

100,00%

Twisted pair laid

15

15

100,00%

Welded fibers

48

48

100,00%

Installed sockets

6

6

100,00%

The power supply is connected to

6

6

100,00%

100,00%