As part of the measures to refuse the use of ADSL communication lines and the transition to a fiber-optic line, it was decided to lay fiber on the territory of the Promtractor PC in the workshops of the BMC, PSC, KOT.
The laying of the fiber-optic line was carried out by the OIC specialists.
As of 12.04.2023, more than 200 users have been transferred
At the first stage of the work, 80 users were connected, including 30 priority ones. At the second stage, it was planned to connect 170 users to the new high-speed fiber-optic communication line (at a speed of 100 MB/s) (now the data exchange rate does not exceed 2 MB/s).
The commissioning of a new fiber-optic communication line made it possible to increase the speed of information exchange and the access of PC Promtractor users to data by about 100 times (it was 2 mb/s became 100 mb/s)
Title |
Total |
Installed |
Done |
Switching cabinets |
17 |
17 |
100,0% |
Laid an optical cable to |
17 |
17 |
100,0% |
Twisted pair laid |
14 |
14 |
100,0% |
Welded fibers |
38 |
38 |
100,0% |
Installed sockets |
14 |
14 |
100,0% |
The power supply is connected to |
17 |
16 |
94,1% |
99,0%
Title |
Total |
Installed |
Done |
Switching cabinets |
21 |
20 |
95,2% |
Laid an optical cable to |
21 |
21 |
100,0% |
Twisted pair laid |
17 |
17 |
100,0% |
Welded fibers |
16 |
16 |
100,0% |
Installed sockets |
17 |
17 |
100,0% |
The power supply is connected to |
17 |
17 |
100,0% |
99,2%
Title |
Total |
Installed |
Done |
Switching cabinets |
6 |
6 |
100,00% |
Laid an optical cable to |
6 |
6 |
100,00% |
Twisted pair laid |
15 |
15 |
100,00% |
Welded fibers |
48 |
48 |
100,00% |
Installed sockets |
6 |
6 |
100,00% |
The power supply is connected to |
6 |
6 |
100,00% |
100,00%